Boston Children's at Brookline Place | Project Schedule

The project schedule below provides information for significant upcoming work for Boston Children’s at Brookline Place. This schedule is updated regularly.

Brookline Place Redevelopment Project

Brookline Place Redevelopment Project

Look Ahead Schedule

March 15, 2019

Current Phase – 3: Construction of 2 Brookline Place (2BP) and 1 Brookline Place (1BP) addition

Upcoming Activities

Weekend Work: 3/16

1 BP: 

  • No work scheduled

2 BP:

  • No work scheduled

Monday, 3/18 Friday, 3/22:

Site Operations:

  • Deliveries ongoing by all trades through Gates 1 and 3 – this will result in crane operations throughout the week

Earthwork

1 BP:

  • Brookline Avenue soils temporarily stored at East Garage

Façade/Roof:

1BP:

  • Low roof coping installation
  • Metal wall panels to be finalized
  • Generator at roof to be completed by EOW
  • Level 1 brick and granite base installation
  • Scuppers and roof drainage to be finalized
  • Northeast and southeast vertical expansion joints (new to existing) to be completed
  • North canopy and vestibule buildout ongoing
  • Exterior finish caulking at building façade

2BP:

  • Rooftop rail installation.
  • Low parapet and AVB installation.
  • Curtain Wall Installation to continue.
  • Terracotta girt and insulation at South Façade.

Building Interior / Utilities:

1BP:

  • Final MEP controls and building controls to be connected and tested
  • HVAC controls installation at penthouse are ongoing
  • Carpet tile install at connectors L2-L6
  • Light fixture installation to continue
  • Firestopping, final taping and sanding of all walls
  • Fuel oil pump connect, power and control (at loading dock)

2BP:

  • Blocking and interior partitions buildout
  • Revised CMU walls at loading dock to be constructed
  • MEP rough installations on-going at all floors
  • Elevator equipment installation
  • Firestopping in final locations
  • Spray fireproofing in remaining areas

Future Activities:

Earthwork

1 BP:

  • Landscaping and hardscaping at 1BP south along Pearl Street (end of March)

2BP:

  • Soil grading at loading dock
  • Catenary light poles
  • Final soils and hardscaping

Façade/Roof:

1BP:

  • Final metal panel penetrations sealed
  • North canopy and vestibule complete
  • Exterior doors/entrances complete

2BP:

  • Terracotta installation to continue
  • Construct loading dock entrance and door
  • Metal panels and louvers at penthouse completed
  • Exterior doors/entrances complete
  • Building is weather tight

Building Interior / Utilities:

1BP:

  • Stair 4 and 5 rubber flooring, egress signs, and paint
  • Ceramic tile at L1-L2 bathrooms
  • Bathroom finishes and partitions
  • Final flooring
  • Final light fixtures
  • Addition lobby complete
  • Final cleaning

2BP:

  • Mechanical, electrical, plumbing, sprinkler rough installations on-going
  • Drywall finish and paint
  • Moisture mitigation at all floors
  • Locker room, bike room and bathroom buildout
  • Final MEP controls and building controls to be connected and tested
  • HVAC controls installation at Penthouse to be completed

More information about Boston Children’s at Brookline Place can be found at http://www.childrenshospital.org/about-us/expansion-and-renewal/brookline-place, and photos from the site can be found here.

The Brookline Place project team mailing address is: One Brookline Place, Suite 521, Brookline, MA 02445.